Custom Home Building Process

A typical 3,000 sq. ft home should be ready in about 6 months, depending upon any delays caused by weather, change orders or other special circumstances.




StepTiming
Lot ClearWeek 1
FoundationWeeks 2-4
Framing, Dry-in Roof, Paint Exterior TrimWeeks 5-9
Rough-in HVAC and Electric, Plumbing Top-out, Speaker & Security WiringWeeks 10-11
Exterior-Brick,Stone and/or Stucco, Sewer Tie-in, Septic Install & RoofingWeeks 12-13
InsulationWeek 14
Dry Wall, Tape, Float & TextureWeeks 15-16
Floor TileWeek 17
Cabinets & Interior TrimWeeks 18-19
Interior PaintWeeks 19-20
Electrical, Plumbing & HVAC Final, Driveway & SidewalkWeeks 21-22
Install Appliances & HardwareWeek 23
Carpet & Wood FloorWeek 24
Final Walk-Through & Touch UpWeek 25
Move-InWeek 26