Custom Home Building Process
A typical 3,000 sq. ft home should be ready in about 6 months, depending upon any delays caused by weather, change orders or other special circumstances.



|
Step | Timing |
Lot Clear | Week 1 |
Foundation | Weeks 2-4 |
Framing, Dry-in Roof, Paint Exterior Trim | Weeks 5-9 |
Rough-in HVAC and Electric, Plumbing Top-out, Speaker & Security Wiring | Weeks 10-11 |
Exterior-Brick,Stone and/or Stucco, Sewer Tie-in, Septic Install & Roofing | Weeks 12-13 |
Insulation | Week 14 |
Dry Wall, Tape, Float & Texture | Weeks 15-16 |
Floor Tile | Week 17 |
Cabinets & Interior Trim | Weeks 18-19 |
Interior Paint | Weeks 19-20 |
Electrical, Plumbing & HVAC Final, Driveway & Sidewalk | Weeks 21-22 |
Install Appliances & Hardware | Week 23 |
Carpet & Wood Floor | Week 24 |
Final Walk-Through & Touch Up | Week 25 |
Move-In | Week 26 |
|